Earned Value Management
PV, EV and AC in both waterfall and Scrum — and the two numbers that tell you whether recovery is a plan or a fantasy.
Earned Value Management — Mastery
The tracking layer. One product — Project Atlas — carried through both Waterfall and Scrum, so you can see the engine is identical and only "done" changes.
Where this sits. EVM comes after you have a baselined plan — a WBS, estimates, a schedule, and a budget. It measures performance against that baseline. If you haven't built the plan yet, start with the WBS & Scheduling chapter; if you don't know your budget mechanics, start with Financials.
💡
Why software needs EVM more than most
The cure for "90% done for three months"
Software has a unique disease: a feature is "almost done," and it stays almost done forever — because the last 10% (edge cases, integration, bugs) is the hard 90% of the effort. Classic tracking compares budget burned vs. money spent and is blind to this. If you've spent 50% of the budget, are you 50% done? In software, almost never — you could be 70% done or 30% done and the spend looks identical.
EVM fixes this by forcing a third measurement: the value of work that is genuinely, verifiably complete — merged-and-tested code, or accepted user stories, never "I'm nearly there." That single discipline is what makes every metric downstream trustworthy.
🔢
The three numbers everything is built from
Learn these three; the rest is arithmetic
PV Planned Value
Budgeted value of work scheduled to be done by now.
BAC × planned %
BAC × planned %
EV Earned Value
Budgeted value of work actually completed & verified.
BAC × verified %
BAC × verified %
AC Actual Cost
What the team has actually cost — salaries, contractors, licenses.
from finance
from finance
BAC = Budget at Completion = the total approved budget. For Project Atlas, BAC = $400k.
The one idea that makes EVM work
EV is valued in budgeted dollars, not what the work actually cost. If a module was budgeted at $20k and you finish it, you earn $20k of value — even if it actually took $30k of engineer time. The extra $10k shows up as a cost problem (in AC), not as bonus progress. This separation is the whole point: it lets you tell apart "we're behind schedule" from "we're over budget" — two problems with completely different fixes.
🧭
The design of this chapter
We check in on Atlas at the halfway point — end of month 5 (Waterfall) or end of sprint 5 (Scrum). The two models are set up to land on identical dollars — PV $200k, EV $160k, AC $200k — so you can see for yourself that the metrics are model-agnostic. Only the definition of "done" differs. Explore Waterfall and Scrum, then hit Metrics to run the numbers, and Calculator to try your own.
🏛️
Waterfall — value from completed WBS phases
"% complete" = sum of finished phases, weighted by budget
In Waterfall, work is a WBS of phases, each with a budgeted slice of the $400k. Earned Value is the budget weight of the phases genuinely finished — not phases "in progress."
| Phase | % of budget | Planned done by M5? | Actually done by M5? |
|---|---|---|---|
| Requirements | 10% | ✅ | ✅ |
| Design | 20% | ✅ | ✅ |
| Development | 40% | half (20%) ✅ | partial (10%) ⚠️ |
| Testing | 20% | not yet | not yet |
| Deployment | 10% | not yet | not yet |
| Cumulative | — | 50% planned | 40% actual |
$200k
PV = 50% planned × $400k
$160k
EV = 40% verified × $400k
$200k
AC = timesheets + contractors
We planned to be through design + half of development, but development hit integration trouble — so only ~a quarter of dev is truly done, yet we've already burned the full $200k we expected to spend by now.
🌀
Scrum — value from accepted story points
Same product, same answer — only "done" is defined differently
In Scrum, scope is a product backlog in story points. The release backlog at baseline = 800 points (the BAC analog). At $400k, that's $500 per point.
PV
Points planned complete by now (from the release plan).
EV
Points actually accepted — meeting Definition of Done, demoed, signed off. Work in progress earns nothing.
AC
Actual team burn — run-rate × sprints elapsed.
| Points | × $500/pt | = Dollars | |
|---|---|---|---|
| Planned by end of sprint 5 | 400 pts | $500 | PV = $200k |
| Actually accepted (done-done) by sprint 5 | 320 pts | $500 | EV = $160k |
| Actual cost (5 sprints × $40k run-rate) | — | — | AC = $200k |
The dollars land identically to Waterfall — PV $200k, EV $160k, AC $200k. That's deliberate: it proves the metrics are model-agnostic. The only thing that changed is how you measure "done": completed WBS phases vs. accepted story points.
Crucial Scrum rule: EV credits only accepted stories. A story that's "code complete but not tested/accepted" earns zero EV. This is Scrum's built-in cure for the 90%-done lie — done is binary and externally verified at sprint review.
⚖️
The Scrum tension interviewers probe
Classic EVM assumes fixed scope; Scrum embraces change
Baseline a release backlog, run EVM against it, then re-baseline for the next release. Within a release, scope is stable enough for the math to mean something.
When the Product Owner adds scope, BAC and PV are reset on a new baseline. You report "against release-2 baseline" so trends stay honest. In Waterfall, re-baselining is a heavyweight change-control event; in Scrum it's routine.
Velocity already counts only accepted stories, which is why Scrum and EVM fit nicely — Scrum hands you a clean, verified EV every sprint at no extra cost.
Dropping that term, plus "I'd track CPI/SPI at the release level while teams stay iterative underneath," signals you understand both worlds.
One-liner to use: "In Scrum I run EVM at the release level off a baselined backlog, credit earned value only for accepted stories, and re-baseline each release — so leadership gets a portfolio-level cost-and-schedule view while the teams stay fully Agile."
📊
The metrics — identical for both models
Plug in PV = $200k, EV = $160k, AC = $200k, BAC = $400k
Variances — subtract. Positive = good.
Schedule Variance
SV = EV − PV = 160 − 200 = −$40k
Behind schedule by $40k of work.
Behind schedule by $40k of work.
Cost Variance
CV = EV − AC = 160 − 200 = −$40k
Over budget by $40k for the work done.
Over budget by $40k for the work done.
The 2×2 that says it all
CV > 0 (under budget)
CV < 0 (over budget)
SV > 0
(ahead)
(ahead)
🟢 Ahead & cheap — ideal
🟡 Ahead but burning cash
SV < 0
(behind)
(behind)
🟡 Behind but frugal
🔴 Behind and over — Atlas is here
Indices — divide. Above 1.0 = good.
Schedule Performance Index
SPI = EV / PV = 160 / 200 = 0.80
Running at 80% of planned pace. In Scrum this is velocity attainment — 320 of 400 planned points = 0.80.
Running at 80% of planned pace. In Scrum this is velocity attainment — 320 of 400 planned points = 0.80.
Cost Performance Index
CPI = EV / AC = 160 / 200 = 0.80
80¢ of value per $1 spent. The king metric — on software it tends to stay flat or worsen after the ~15–20% mark.
80¢ of value per $1 spent. The king metric — on software it tends to stay flat or worsen after the ~15–20% mark.
📈
Forecasting — where Atlas actually lands
The part executives care about most
| Metric | Formula | Atlas value | Reading |
|---|---|---|---|
| EAC | BAC / CPI | 400 / 0.80 = $500k | Realistic final cost |
| ETC | EAC − AC | 500 − 200 = $300k | Cash still needed |
| VAC | BAC − EAC | 400 − 500 = −$100k | Projected overrun |
| TCPI | (BAC−EV)/(BAC−AC) | 240 / 200 = 1.20 | Efficiency needed to save the budget |
TCPI is the lie detector. We've been running at CPI 0.80, and TCPI says we'd now need to run at 1.20 to still hit $400k. A team stuck at 0.80 will not flip to 1.20. Translation: the original budget is gone — re-baseline and escalate now, at the halfway point, not at delivery.
🎯
Three EAC variants — pick by situation
| Formula | Use when… |
|---|---|
| EAC = BAC / CPI | Past cost performance will continue — most common, most honest default |
| EAC = AC + (BAC − EV) | The overrun was a one-off; remaining work will hit budget |
| EAC = AC + (BAC − EV)/(CPI × SPI) | Both cost and schedule pressure will persist — most pessimistic |
🗺️
Waterfall ↔ Scrum mapping
The table to memorize
| EVM concept | Waterfall (Atlas) | Scrum (Atlas) |
|---|---|---|
| BAC | Total project budget ($400k) | Release scope: 800 pts / $400k baseline |
| Unit of progress | Completed WBS phases, budget-weighted | Accepted story points (Definition of Done) |
| PV | Budget scheduled by this date | Points planned by this sprint |
| EV | Value of phases completed | Points accepted × $/point |
| AC | Timesheets + contractor + license | Team run-rate × sprints elapsed |
| SPI | Schedule adherence | Velocity attainment |
| CPI | Cost efficiency | Cost per accepted point vs. baseline |
| Re-baselining | Formal change request, rare | Expected — per release / PI |
| "% complete" risk | Optimistic phase reporting | WIP counted as done (avoid) |
⚠️
The hard part: measuring "% complete" honestly
Every number downstream is fiction if EV is fiction
| Method | How it credits EV | Best for |
|---|---|---|
| 0/100 | Nothing until the item is fully done | Scrum stories, small tasks — the safest default |
| 50/50 | 50% on start, 50% on completion | Medium Waterfall work packages |
| Milestone / weighted | Credit at defined checkpoints | Long phases with module milestones |
| % effort (avoid) | Self-reported % | Danger where the 90%-done lie lives |
Scrum's Definition of Done is effectively a strict 0/100 rule — which is exactly why Agile EVM tends to be more trustworthy than self-reported Waterfall progress.
🚧
Limitations to name in an interview
What EVM can't do
SV/SPI are in dollars/points, not time — and SPI drifts to 1.0 near the end (fix: Earned Schedule)
Garbage in, garbage out — optimistic % complete = lying metrics
No quality/value signal — you can be green and still shipping the wrong thing
Diagnostic, not causal — tells you that you're behind, not why
What it does brilliantly
Separates a schedule problem from a cost problem — different fixes
Surfaces the overrun at the halfway point, in numbers a CFO trusts
TCPI gives an honest reality check on whether the budget is recoverable
Works identically across Waterfall and Scrum
⚙️
Live EVM calculator
Enter your four inputs — every metric and the verdict update live. Pre-loaded with Project Atlas.
Units are your own ($k, $, or story-point dollars). All metrics use the standard PMI formulas.
Variances & indices
SV EV − PV——
CV EV − AC——
SPI EV / PV——
CPI EV / AC——
Forecast at completion
EAC BAC / CPI—
ETC EAC − AC—
VAC BAC − EAC——
TCPI (BAC−EV)/(BAC−AC)—
—
🧠
Test yourself
0 / 8